Finally, we have colored stucco. A couple days after the stucco was finished, the soffit and fascia was finished. The color of the stucco is Dryvit Spectrum Brown and the soffit and fascia is black. I think it looks really good, on the other hand I may have just made it black inspite of everyone telling me I shouldn't. Now that it's done, we can play monday morning quarterback. Everyone who thinks it looks great say "Yea" and those who thinks it is aweful say "Nay." Those who are indifferent are cursed to a life of indecisiveness.
Wednesday, February 28, 2007
Thursday, February 22, 2007
Some Stucco
Stair Building
Wednesday, February 21, 2007
No pictures?
For some reason, my pictures are not uploading. For the past month we have insulated, installed drywall, done the drywall texture, installed the finish trimwork, put stucco on the exterior, and prepared for paint. We should have soffit, fascia and gutter installed by the end of the week and the whole house should be primered.
I ordered the locksets for the doors, picked up a fridge, hood, range, and a dishwasher. The cabinets are ordered and we picked out the wood colors and paint colors. Things are moving along, too bad I can't get my pictures to upload.
I ordered the locksets for the doors, picked up a fridge, hood, range, and a dishwasher. The cabinets are ordered and we picked out the wood colors and paint colors. Things are moving along, too bad I can't get my pictures to upload.
Sunday, January 21, 2007
I'm always playing catch up
Thursday, January 11, 2007
A Four Way to be Proud of
Oh yeah, thats my furnace room. Women can have their kitchens and bathrooms and living rooms and sewing rooms and whatever. This is a man room. What you see is the guts and the glory of any house. On the left is two 50 gallon water heaters, in the back is a 96.6 percent variable speed furnace and you can't see the gas distribution, water distribution or electrical distripution panel, but trust me, it is quite the setup.
We got the 4 way inspection last week (mechanical, electrical, plumbing, framing) and passed with flying colors. Well, almost. It seems my free labor plumber (my dad) flunked his drainage test. We had 4 leaks and we only filled up 15% of the system with water. We had to drain the water quick because if it froze in the pipes, we would have major problems. I have a reinspection tomorrow, I'm crossing my fingers. The inspector gave us the go ahead with insulation last week, so we insulated on Tuesday. I'll have to take some pictures of it before drywall is installed on Tuesday.
I'm in Las Vegas today and for the next week I will be supervising the construction of a house/Disneyland Resort. The superintendent has to leave for a couple days and I am filling in. Here is a link to that house www.piratescovelv.blogspot.com if you have a couple minutes to check it oug. It's a pretty incredible job. Maybe one day I can have waterslide in my backyard.
We got the 4 way inspection last week (mechanical, electrical, plumbing, framing) and passed with flying colors. Well, almost. It seems my free labor plumber (my dad) flunked his drainage test. We had 4 leaks and we only filled up 15% of the system with water. We had to drain the water quick because if it froze in the pipes, we would have major problems. I have a reinspection tomorrow, I'm crossing my fingers. The inspector gave us the go ahead with insulation last week, so we insulated on Tuesday. I'll have to take some pictures of it before drywall is installed on Tuesday.
I'm in Las Vegas today and for the next week I will be supervising the construction of a house/Disneyland Resort. The superintendent has to leave for a couple days and I am filling in. Here is a link to that house www.piratescovelv.blogspot.com if you have a couple minutes to check it oug. It's a pretty incredible job. Maybe one day I can have waterslide in my backyard.